We are currently carrying out the site preparation, enabling and earthworks for
Part C of Package 1.
Our scope of work includes mobilising the workforce and construction plant required for the project, establishing temporary site facilities, and providing and maintaining access roads to ensure continuous vehicular access throughout the site. It also includes carrying out drainage and flood management works and addressing damage caused by flood discharges from adjacent wadis .
The works include clearing all obstructions from approximately 3.84 million m² of existing forest and farmland, relocating and replanting selected trees,
constructing perimeter and diversion roads and drainage channels, and constructing the western protection dike. All works are being carried out in accordance with the project specifications and applicable standards, while meeting the project’s quality requirements and complying with health and safety requirements throughout